Explainer

Round Four, Explained

Montgomery owes 260 affordable units for 2025 to 2035. The plan it adopted in 2025 put most of them on the Kenvue site. The plan it adopted in 2026 builds almost nothing and instead keeps 210 existing affordable homes affordable for another generation. This is how that works, what it rests on, and which parts of it are not yet settled.

  • This page does not describe the housing case as finished. A settlement exists; no compliance hearing has been held; no certification has issued.
  • Where the plan depends on an agreement that has not been made, it is said so in the same sentence as the number.

Checked against the primary record on . Every figure on this page is sourced at the foot of the article.

At a glance

The prospective obligation
260 units Montgomery's Fourth Round share, set by a court order in late March 2025. Township resolutions date that order inconsistently — March 26 in one, March 27 in another.
What the amended plan claims
275 credits 210 preserved units plus 65 bonus credits, as the board planner summarised it on March 9, 2026.
The margin
Plus 15 Fifteen credits above the obligation. That is surplus, not slack: part of the 275 is conditional.
The round
2025 to 2035 With a state midpoint review in 2030 and compliance mechanisms completed or underway by 2035.
Compliance hearings held
None The settlement with Fair Share Housing Center is not final until a court approves it at one.
What replacing Kenvue was said to need
About 706 units Calculated aloud in June 2025, when the site was still in the plan and the township had no alternative in reserve.

Every figure here is sourced in the numbered list at the foot of the page.

The obligation

What the Fourth Round is

Every New Jersey municipality has a constitutional obligation to provide its fair share of the region's affordable housing. The Fourth Round is the current ten-year cycle.

Montgomery entered the cycle the way most towns did. It filed a declaratory-judgment action and joined the court-run Affordable Housing Dispute Resolution Program on January 29, 2025, under Docket No. SOM-L-153-25. A court order in late March 2025 set its obligations — a present need of 73 units and a prospective need of 260 units for 2025 to 2035. Township resolutions date that order inconsistently: the March 19, 2026 minutes say March 26, 2025; the June 18, 2026 minutes say March 27. This page covers the prospective need.

The round has a shape as well as a number. Compliance mechanisms are to be completed or underway by 2035, with a state midpoint review in 2030. The statutory deadline to adopt a Housing Element and Fair Share Plan was June 30, 2025; Montgomery's board adopted its first Fourth Round plan on June 26, four days inside it.

Amending a plan mid-round is not unusual and Montgomery has done it before: the Third Round plan was adopted in 2008 and amended in 2010, 2018 and 2020. The township cited that history when it amended the Fourth Round plan in 2026. Its stated reason was that circumstances had changed since June 2025 in a way that let it extend affordability controls on additional existing units, so it would remove some previously proposed inclusionary developments and prioritise preservation instead.

Source Township Committee — February 19, 2026 watch the township video from 16:43 The township planner's affordable housing update, including the round dates and the reason given for amending.

The plan

How the 260 is met

Almost entirely by keeping existing affordable homes affordable, rather than by building new ones.

Affordable homes are not permanently affordable. Each one carries controls — recorded restrictions that cap what it can be rented or sold for and who may live in it — and those controls expire. When they lapse, the home joins the market and the town loses the credit. The amended plan works by paying to extend controls that were about to expire, on four existing developments, for another thirty years.

The four developments carrying Montgomery's Fourth Round obligation under the amended plan.

Pike Run

Family rental

Units carried in the plan
96
Credits claimed
58, the state cap for age-restricted units; 75 with bonuses
On site overall
Not stated in these terms
Where it stands
Controls extended by resolution, November 13, 2025

McKinley Court

Senior rental

Units carried in the plan
96
Credits claimed
58, the state cap for age-restricted units; 75 with bonuses
On site overall
Not stated in these terms
Where it stands
Controls extended by resolution, November 13, 2025

McKinley Commons

Ownership

Units carried in the plan
96
Credits claimed
58, the state cap for age-restricted units; 75 with bonuses
On site overall
Not stated in these terms
Where it stands
Controls extended by resolution, November 13, 2025

Montgomery Glen

Ownership

Units carried in the plan
96
Credits claimed
58, the state cap for age-restricted units; 75 with bonuses
On site overall
Not stated in these terms
Where it stands
Controls extended by resolution, November 13, 2025

On March 9, 2026 the board planner summarised the result as 210 preserved units plus 65 bonus credits: 275 credits against an obligation of 260, a margin of 15. News reporting at the time used 273; this page follows the minutes. Blank or qualified cells mean a figure was not given in those terms, not that it is zero.

Preservation is not free. On November 13, 2025 the Township Committee introduced a $1.1 million bond ordinance, #25-1766, to fund the extensions — $1,100,000 in all, of which $650,000 comes from the township's COAH (affordable housing) trust fund and $450,000 is authorised as bonds or notes — and adopted the first resolutions extending controls, at McKinley Court and Montgomery Glen. It also ratified a settlement agreement the same night. The bond ordinance was finally adopted on December 4, 2025.

Three sites came out of the plan to make room for this approach: the E. Kahn site at 199 Grandview Road, 23 Orchard Road, and Thrive Assisted Living, whose credits were deferred to a future round.

Source Township Committee — November 13, 2025 watch the township video from 33:18 The bond ordinance that pays for the extensions.

The soft spots

What is not settled

Two things in the paragraphs above are less firm than the round numbers make them look. Both are on the public record, and neither is a matter of opinion.

Source Township Committee — September 17, 2026 watch the township video The attorney's report on the settlement, the compliance hearing and the immunity risk.

Plain language

The mechanics

Five terms do most of the work in this dispute, and three of them are routinely misunderstood.

A Master Plan does not change zoning

A Master Plan is a policy document: it says what the township intends. It does not by itself change what anyone may build. Zoning changes are a separate Township Committee process, with its own ordinance and its own public hearing. A housing element sits inside the Master Plan; the implementing ordinances that follow it are where the legal effect lives.

Montgomery's first Master Plan was adopted in 1971. The last reexamination was in 2017, and the Municipal Land Use Law requires one every ten years, so the next is due in 2027; the township said in February 2026 that the process was expected to begin that year and that it had won a significant planning grant to fund it.

Extending affordability controls

The controls on an affordable home are recorded restrictions with an end date. Extending them means persuading — and usually paying — the owner to accept a new, longer term, typically thirty years. The unit does not change; what changes is how long it stays affordable. Each extended unit counts toward the obligation, and the state allows additional bonus credits on top, which is how 210 units produce 275 credits.

The essential point, and the one that explains the last two years of Montgomery politics: where the units belong to a private landlord, an extension requires the owner's agreement. The township approached Pike Run's owner in 2025 and the owner did not agree; staff told the Planning Board that the recorded documents give the township no right to sue over an extension. Where the township already holds the deed restriction, as at McKinley Commons and Montgomery Glen, it extended the controls by resolution and used a $10,000 payment as the homeowner's incentive to sign.

A builder's remedy lawsuit

If a municipality has no court-approved plan for meeting its obligation, a developer can sue. If the developer wins, a court — not the township — can approve a project at a density the local zoning does not permit, usually in exchange for an affordable set-aside. The township loses the ability to say where and at what scale.

Immunity, and why it is the whole game

While a municipality is inside the court process with a plan in good standing, it is immune from those suits. Montgomery's immunity was extended by court order in early March 2026 to carry it through the amendment process, and the program judge recorded that but for time constraints the township seemingly had a compliant plan. Immunity is not permanent, though, and it is what the township attorney warned could be lost if no compliance hearing is held.

The 2030 midpoint review

A statutory checkpoint halfway through the round, at which a municipality must show it is on track. For Montgomery it doubles as the fallback date for the conditional McKinley extensions, whose controls run to 2032.

The order the steps come in

The Fourth Round sequence, and where Montgomery has got to Five steps in order. The first three are complete: a declaratory judgment filed on January 29, 2025; a 260-unit prospective obligation declared by township resolution on January 27, 2025 and accepted by court order that March; and a Housing Element and Fair Share Plan adopted June 26, 2025 and amended March 9, 2026. The last two are drawn dashed because they have not happened: the fairness and compliance hearing, and the Judgment of Compliance and Repose. 1 Declaratory judgment Filed January 29, 2025 2 The number is fixed Township resolution, January 27, 2025: 260 units 3 Housing Element and Fair Share Plan Adopted June 2025; amended March 2026 4 Fairness and compliance hearing Not yet held 5 Judgment of Compliance and Repose Not issued
  1. Declaratory judgment. Filed January 29, 2025. Complete.
  2. The number is fixed. Township resolution, January 27, 2025: 260 units. Complete.
  3. Housing Element and Fair Share Plan. Adopted June 2025; amended March 2026. Complete.
  4. Fairness and compliance hearing. Not yet held. Not reached.
  5. Judgment of Compliance and Repose. Not issued. Not reached.
Montgomery is between steps three and four. The plan exists and has been amended; the hearing that would make it binding has not been held, which is why the township’s protection from builder’s-remedy suits is still described as contingent.

The turn

The Pike Run reversal

The development that now carries more of Montgomery's obligation than any other was not in the 2025 plan at all, because its owner would not agree to extend the controls.

At the June 23, 2025 hearing, staff were asked about Pike Run directly. They said Pike Run has 210 affordable units with controls expiring inside the Fourth Round, that the township had approached the owner, and that the owner “were not able to agree to extend the controls.” Pike Run was therefore not in the 2025 plan, which leaned on the Kenvue site instead — though no one on the record put those two facts as cause and effect.

Pressed again at the June 26 continuation, staff added detail: because the units are rentals in single ownership, the owner has to be willing, and the owner was not; investors who put money into the property thirty years earlier expected their return to come when the units shifted to market rate, and the township had no legal means to compel an extension.

Five months later the position had changed. At the November 13, 2025 meeting the township attorney reported an agreement in principle with the owner of Pike Run, which the township was working to turn into a memorandum of understanding; the mayor thanked staff for a route that had been “getting harder because of not having the builder of Pike Run willing to work with us,” and described the prize: “if we can get all of these extensions, that means we do not need to have any construction.”

On December 4, 2025 the attorney put the same thing in its narrowest terms: no agreement had been executed, but there was an agreement in principle — a verbal agreement — for an extension of at least 96 units. That is the form it was still in when the township notified the court program and the parties, by letter, that it would amend its plan.

By February 2026 Pike Run was the centrepiece of the amended plan, carrying 144 of its 275 credits.
2026 Amended Fourth Round Fair Share Plan, as summarised by the board planner on March 9, 2026

The public record does not explain why the owner's position changed. The adopted plan says only that the owner “had not previously expressed interest” and that discussions after the June 2025 adoption made the amendment possible. No meeting, minute or filing that this site has reviewed gives a reason. It is a genuine gap, and this page will not fill it with a guess. If the answer surfaces — in the settlement documents, at a compliance hearing, or from the owner — it belongs here.

Source Planning Board — June 23, 2025 watch the township video from 59:20 Staff answer the Pike Run question.

June 2025

There was no backup plan

Asked at the 2025 hearing what would happen if the Kenvue site fell through, staff gave an unusually direct answer.

Past plans, they said, had sometimes carried backup alternatives. This one did not: “we didn't have any backup alternatives for this plan.” The board would simply have to come back and amend.

The board planner then did the arithmetic aloud. Replacing the Kenvue site would require sites capable of about 706 units, because losing it meant losing three things at once: the affordable units built on the site, the bonus credits attached to it, and the off-site control extensions the developer was to have funded.

It is worth holding that number next to what actually happened. The replacement, when it came, required no new construction at all — the township said in November 2025 that if it could secure every extension it was chasing, no building would be needed. The 706-unit figure was an honest answer to the question as it was asked in June 2025; it was not a forecast, and it did not turn out to describe the path the township took.

Source Planning Board — June 23, 2025 watch the township video The contingency question and the 706-unit calculation.

November 2025 to March 2026

How Kenvue came out

Mediation, an announcement, an information session, a blizzard, and an adoption vote in which the site is never mentioned.

The first mediation session with the court program was held on November 14, 2025. On December 4, 2025 the township attorney told the Committee that Montgomery had notified the program and the parties, by letter, that it would amend its plan. The amended plan was presented to the Planning Board at an information session on February 9, 2026, posted online on February 13, and carried into the Township Committee as an implementing ordinance on February 19. The Planning Board hearing noticed for February 23 was cancelled by a blizzard.

The court steps ran alongside. The program issued its decision on March 4, 2026 and the judge's order accepting it followed on March 5. The Planning Board held the public hearing and adopted the amended plan on March 9, 2026, and the Township Committee endorsed it by Resolution #26-3-113 on March 19. The filing deadline of March 15 was expected to slip: the township planned to ask the court for extra days under the blizzard emergency, noting it was far from the only town making that request.

The clearest evidence of the outcome is an absence. At the March 9 adoption hearing the Kenvue site is never named. It is simply not in the plan the board adopted. What has happened on the property since is the subject of our Kenvue explainer.

Source Planning Board — March 9, 2026 watch the township video The public hearing and adoption of the amended plan.

Ahead

What to watch

Four dates and one hearing decide whether the amended plan holds.

  • The compliance hearing. Not scheduled. The judge has said he will not entertain one until the township has sat down with E. Kahn Development. Until it happens, the settlement is not final and immunity is contingent.
  • The McKinley extensions. Conditional on discussions with the developer; the controls run to 2032, and the 2030 midpoint review is the fallback checkpoint.
  • The 2030 midpoint review. The state checkpoint at which Montgomery must show it is on track.
  • The 2027 Master Plan reexamination. Due under the Municipal Land Use Law, with the process expected to have begun in 2026.

All of this is decided in public meetings. The Township Committee generally meets on the first and third Thursday of the month; the Planning Board generally on the second and fourth Monday; the Zoning Board of Adjustment generally on the fourth Tuesday. All three move and skip meetings, so check the township's board meeting calendar before you go.

This story on the timeline

Each entry carries its own citations and, where a meeting exists, a deep link into the township video.

  1. Milestone Planning Board opens the Fourth Round hearing — 417 units on the Kenvue siteThe Planning Board opened its public hearing on the Fourth Round Housing Element and Fair Share Plan, whose two inclusionary sites Headline News Montgomery totalled at 597 units, and which put 417 of them, 70 affordable, on the former Kenvue campus. The meeting ran about three hours — roughly the first half-hour a presentation, the rest questions, never reaching public comment — and the hearing was carried to June 26.
  2. Resolved Planning Board adopts the 2025 Fourth Round plan, eight to oneAfter roughly two more hours of public comment, the Planning Board adopted the Fourth Round Housing Element and Fair Share Plan dated June 13, 2025 — the plan carrying 417 homes on the Kenvue campus — on a roll call of eight ayes and one no, four days before the state deadline.
  3. Resolved A $1.1 million bond and the first extensions of affordability controlsThe Township Committee introduced a $1,100,000 bond ordinance to pay for extending affordability controls on existing affordable homes, adopted the first two extension resolutions covering 54 owner-occupied units, and adopted a resolution ratifying a settlement agreement. Every recorded vote was 5-0.
  4. Milestone First mediation session; the township signals it will amend its planAt the first settlement conference in the Round Four case, and in a letter that followed, Montgomery notified the state's dispute resolution program and every interested party that it would amend its housing plan — because an agreement in principle with the owner of Pike Run, together with extensions already approved elsewhere, made the inclusionary sites unnecessary.
  5. Milestone The township says the Kenvue site is coming out of the housing planIn an affordable housing update moved to the top of the agenda, the township attorney said Montgomery had notified the court program it would amend its plan, and that with the Pike Run extensions no other development would remain in it — naming the Kenvue site and Thrive. 23 Orchard Road came out too, though she did not name it that night. The Committee then adopted the $1.1 million bond ordinance.
  6. Milestone Planning Board information session on the amended planA 30-minute information session, not a hearing: staff walked the Planning Board and the public through the draft amendment that drops the E. Kahn/Kenvue site, 23 Orchard Road and Thrive Assisted Living in favour of extending affordability controls on existing units. No vote was taken.
  7. Pending Program judge reports no consensus; a fairness hearing comes nextThe township attorney reported that the program judge had told the Mount Laurel judge no consensus was reached with the objectors, and that the next step is a fairness hearing before any order issues. The Committee adopted the rewritten Chapter 15 ordinance and the amended spending plan, each 5-0.
  8. Resolved Planning Board adopts the Amended Fourth Round plan, 8-0After a hearing of about twenty minutes at which no member of the public spoke, the Planning Board adopted the 2026 Amended Fourth Round Housing Element and Fair Share Plan on an 8-0 roll call — 275 credits from 210 preserved units plus 65 bonus credits, against an obligation of 260. The Kenvue site carries no credits in it.
  9. Resolved Township Committee endorses the amended planThe Township Committee endorsed the 2026 Amended Fourth Round Housing Plan Element and Fair Share Plan by Resolution #26-3-113, adopted 3-0 as part of the consent agenda with Ahn and Deputy Mayor Barragan absent, completing the municipal side of the amendment.
  10. Pending Committee authorizes a settlement with Fair Share Housing CenterReturning from executive session at 10:18 p.m., the Township Committee adopted Resolution #26-6-194 authorizing a written Fourth Round settlement agreement with Fair Share Housing Center on the terms of the amended plan the Planning Board adopted in March. A settlement is not a judgment.
  11. Pending The housing case is not over: no compliance hearing, no certificationOn the same night, the township attorney said Montgomery has reached a settlement with Fair Share Housing Center but that it is not final until a court approves it at a compliance hearing — one the judge would not hold until the township sat down with E. Kahn Development, a meeting that has now taken place. Without a hearing, the attorney said, the township could lose its immunity from builder's-remedy lawsuits.

The documents behind this page

Primary records, linked where the township, the courts and the planners publish them.

Sources

Where each claim on this page comes from. Where reporting and the primary record disagree, the primary record is used and the disagreement is noted.

  1. 2026 Amended Fourth Round Housing Plan Element and Fair Share Plan The adopted plan itself, prepared by Clarke Caton Hintz.
  2. Planning Board minutes, March 9, 2026 The adoption hearing. The source of the 210 preserved units plus 65 bonus credits figure, and of the disclosure that the McKinley extensions are conditional.
  3. Township Committee minutes, March 5, 2026 Records that no consensus was reached on the objections and that a fairness hearing comes next.
  4. Township Committee minutes, March 19, 2026 Resolution #26-3-113 endorsing the amended plan, with the full procedural chain in its recitals.
  5. Township Committee meeting video, February 19, 2026 The planner's affordable housing update: the round dates, the 2030 midpoint review, the Master Plan history and the reason given for amending.
  6. Planning Board meeting video, June 23, 2025 The Pike Run exchange, the absence of a backup plan and the 706-unit calculation are all in this hearing.
  7. Township Committee meeting video, November 13, 2025 The $1.1 million bond ordinance and the first resolutions extending controls.
  8. Township Committee meeting video, December 4, 2025 The announcement that the Kenvue site comes out of the plan, and the bond ordinance adopted the same night.
  9. Planning Board meeting video, March 9, 2026 The public hearing and adoption of the amended plan.
  10. Township Committee meeting video, September 17, 2026 The township attorney's account of the Fair Share Housing Center settlement, the compliance hearing and the risk to immunity.
  11. New Jersey Courts Administrative Directive #14-24 The rules for the court-run Affordable Housing Dispute Resolution Program.
  12. Montgomery Township: Round Four Housing Process Explained The township's own narrative and its index of Round Four material.
  13. The Monty News: Montgomery Township to amend affordable housing plan
  14. Montgomery Township: board meeting calendar The live calendar. All three boards move and skip meetings.