199 Grandview Road in Skillman is the former Johnson & Johnson research campus, later Kenvue's. It runs to 382.771 acres, its late-modern headquarters building is one residents have asked the township not to demolish, and it is nearly empty. In fifteen months it has been written into a housing plan as the site of 417 homes, written back out, sold, litigated over, and — since September 17, 2026 — made the subject of a redevelopment study that the property's owner asked for and is paying for.

  • This page states no damages figure for the data-center lawsuit. The $300 million claim that circulated in August 2026 belongs to a different case in another municipality, and the township said so on the record.
  • The development concepts compared below were presented months apart, on different occasions. They are alternatives, not versions of one plan, and their numbers are not interchangeable.

Checked against the primary record on . Every figure on this page is sourced at the foot of the article.

At a glance

The whole holding
382.771 acres Block 14001 Lot 2 and Block 13001 Lot 15, as stated in the 2025 Fair Share Plan.
Limited Manufacturing core
About 257 acres The developable heart of the campus, as the developer's engineer described it on the record.
Proposed, then removed
417 units 70 of them affordable. Written into the 2025 housing plan; absent from the amended plan adopted March 9, 2026.
The September 17, 2026 vote
4 to 0 Both resolutions carried with Committeeman Mike Martin absent. Not a five-member vote, and not a tie-breaker.
What the study covers
Block 14001, Lot 2 One lot, not the whole campus. The designation contemplated is non-condemnation, so it carries no eminent-domain power.
The annual tax gap the township expects
About $1.4 million Mayor Singh's figure, given September 17, 2026, for the year after Kenvue ceases operations at the site.

Every figure here is sourced in the numbered list at the foot of the page.

The ground

What the property is

Three different numbers have been used in public for the size of this campus. They are all correct, and they describe different things.

The 2025 Housing Element and Fair Share Plan gives the property as 382.771 acres, comprising Block 14001 Lot 2 and Block 13001 Lot 15. E. Kahn's engineer, Matt Adams, describing the same holding aloud to the Planning Board in September 2025, broke it into three tax parcels: roughly 125 acres north of Grandview Road, split about one-third into the Mountain Residential 10-acre zone and two-thirds into the R5 five-acre zone; a main parcel of, in his words, 257 plus or minus acres in the Limited Manufacturing zone; and a parcel a little over two acres to the south.

The third figure, 160 acres, is not an official subdivision of anything. It comes from a resident reading the assessor's records aloud at the June 23, 2025 hearing: former Mayor Devra Keenan put the commercially assessed (class 4B) portion of the main parcel at about 160 acres, at a net assessed value of roughly $41 million, with a further 97 acres nearby carried as farm-qualified. The observation that those two figures land near the 257 was hers, made live from the records that night. No township document divides the Limited Manufacturing core that way.

The Grandview Road campus, by parcel A horizontal bar divided in proportion to acreage: about 257 acres of Limited Manufacturing land forming the core of the campus, about 125 acres north of Grandview Road in the Mountain Residential and R5 residential zones, and a southern parcel of a little over two acres shown at a minimum width. 382.771 ACRES IN TOTAL ~257 acres ~125 Limited Manufacturing core North of Grandview
  • About 257 acres — the Limited Manufacturing core, described on the record as a “257 plus or minus acre” main parcel. Within it, former Mayor Devra Keenan, reading the assessor’s records aloud at the June 23, 2025 hearing, put roughly 160 acres in the commercial class and an adjoining 97 acres in farm qualification.
  • About 125 acres north of Grandview Road — roughly one-third in the Mountain Residential 10-acre zone and two-thirds in the R5 five-acre zone.
  • A little over two acres to the south, drawn here at a minimum width so it is visible at all.
  • The September 2026 redevelopment study covers only Block 14001, Lot 2 — not the whole holding.

The 2025 Housing Element and Fair Share Plan puts the property at 382.771 acres across Block 14001 Lot 2 and Block 13001 Lot 15. The three-parcel breakdown above is the developer’s planner’s approximation, given aloud at the September 8, 2025 Planning Board meeting, and does not add up to that total exactly. The 160- and 97-acre split within the main parcel comes from a different meeting: former Mayor Devra Keenan read it out of the assessor’s records at the June 23, 2025 hearing. That is her arithmetic on the night, not an official subdivision of the Limited Manufacturing core; no township document divides it that way.

Source Planning Board — September 8, 2025 watch the township video from 10:36 The conceptual presentation of the Kenvue site plans begins here.

Source Planning Board — June 23, 2025 watch the township video from 1:50:20 Devra Keenan reads the acreage and assessed values out of the assessor's records.

The campus was Johnson & Johnson's, and later Kenvue's. Residents told the Township Committee on July 17, 2025 that its late-modern headquarters building was designed by Henry N. Cobb and W. Steven Wood of I.M. Pei & Partners, with oversight by Pei himself. The township's own 2025 housing plan did not acknowledge that attribution: it found there are “no historic or architecturally important sites or buildings on the property.” In 2024 Kenvue told the township it was moving its offices to a smaller footprint in Summit, and it has been winding the campus down ever since — the last of its operations end in 2026. The township's affordable-housing counsel told the Township Committee on September 17, 2026 that Kenvue would cease operations at the site by the end of the year.

One detail from the middle of the story is worth keeping: in June 2025, while the township was planning 417 homes on the property, the buyer had not closed. Former Mayor Devra Keenan told the board the deed still read Johnson & Johnson; staff would say only that they were working with “the contract purchaser,” though the plan itself named E. Kahn Development as the developer.

June 2025

417 units on the campus

Montgomery's Fourth Round housing plan put more than two-thirds of the homes in its two inclusionary sites on one empty site.

A legal notice published on June 12, 2025 set a Planning Board hearing on the Fourth Round Housing Element and Fair Share Plan. Its two inclusionary sites came to 597 units between them, 106 of them affordable homes built on site — a total Headline News Montgomery reported, rather than one the plan states. The Kenvue site alone carried 417 residential units, 70 of them affordable, and would have required the campus to be demolished; the other 180 units, 36 affordable, went to 23 Orchard.

For scale: at the June 23, 2025 hearing former Mayor Devra Keenan, working from the acreage she had just read out of the assessor's records, said that portion of the site could support roughly 16 to 80 homes under its existing zoning. The plan's number was not an increment on what the zoning allowed. It was a different order of thing, and it depended on the site being treated as an inclusionary development.

The hearing on June 23, 2025 ran about three hours in all — roughly the first half-hour the planner's presentation, the rest questions — and it never reached the formal public comment period. It ended with no vote and was carried to June 26 at 5 p.m., four days before the June 30 statutory deadline to adopt a plan. The Planning Board adopted the plan at that continued hearing.

Source Planning Board — June 23, 2025 watch the township video About three hours, mostly questions; no vote, and the hearing carried to June 26.

Summer 2025

The response

The objection that carried was not to affordable housing. It was to the process, and to the density.

Former Mayor Devra Keenan set the 417 units against what the zoning actually allowed — 16 homes, or 32, or at most 80: “Why would we all of a sudden say, oh, 412 is totally fine? That's very problematic.” Resident Shellie Jacobson raised the demolition of the I.M. Pei building. Others asked what the township would do if the site fell through, and were told there was no alternative in reserve.

It sounds to me like this is a fait accompli… do they really amount to anything?
Resident George DeSanctis, Planning Board hearing, June 23, 2025, as reported by Headline News Montgomery

On July 17, 2025 residents took the same case to the Township Committee. Save Montgomery — a grassroots group of Montgomery Township residents, represented by the attorney Bruce Afran — formed around that position: not opposed to affordable housing, opposed to the process and to high-density development on this site.

Source Township Committee — July 17, 2025 watch the township video Mayor Singh was absent; Deputy Mayor Barragan chaired.

November 2025 to March 2026

Out of the plan

Mediation in November 2025, an announcement in December, an amended plan in February, adoption in March.

The first mediation session with the court program was held on November 14, 2025. On December 4, 2025 the township attorney told the Township Committee that Montgomery had notified the program and the parties, by letter, that it would amend its plan, and that with the Pike Run extensions counted, no other development — the Kenvue site included — needed to stay in it. The mechanics had been put in place three weeks earlier: on November 13 the Committee introduced Ordinance #25-1766, appropriating $1,100,000 — $650,000 from the township's COAH trust fund and $450,000 authorised as bonds or notes — and adopted resolutions extending affordability controls at McKinley Court and Montgomery Glen. Preserving existing affordable homes would replace building new ones.

What made that arithmetic work was Pike Run. Staff had told the Planning Board on June 23, 2025 that the township approached the owner of its 210 affordable rentals and that the owner “were not able to agree to extend the controls.” By November 13, 2025 the township attorney was reporting an agreement in principle with that owner, which the township was working to turn into a memorandum of understanding; on December 4 she described it as a verbal agreement in principle, not yet executed, covering at least 96 units. The public record does not explain why the owner's position changed. Nothing on this site offers a theory about it. The sequence is set out in full on the housing page.

The amended plan was presented at a Planning Board information session on February 9, 2026, posted on February 13, and carried by the Planning Board on March 9 after the February 23 hearing was cancelled by a blizzard. The Township Committee endorsed it on March 19. Two other sites came out at the same time: 23 Orchard Road, and Thrive Assisted Living, whose credits were deferred to a future round.

The clearest measure of the change is negative. At the March 9, 2026 adoption hearing the Kenvue site is never mentioned. It simply is not in the plan the board adopted. How the 260-unit obligation is met instead is the subject of our Round Four explainer.

October 2025 onward

A new owner

The sale closed in or around December 2025 or early January 2026 — the only dating on the public record — and the buyer had already begun filing for the site before it closed.

In October 2025, before closing, E. Kahn filed a general development plan for light industrial use. The Planning Board did not hear it: Montgomery has no ordinance authorising general development plan review, and no standards for one. The developer sued the board over the refusal. Board attorney Karen Cayci explained the appeal of the instrument — a general development plan takes less documentation than a full application and, where the ordinance exists, can shield a project from later zoning changes for years.

The purchase completed in or around December 2025 or early January 2026; that is the only dating the public record gives. Who holds the deed now is itself contested: a resident told officials in February and again in September 2026 that the deeds of record name four single-member limited liability companies rather than E. Kahn Development Corp., while the township attorney said in September 2026 that the site “is solely owned now by” E. Kahn Development. This page reports the disagreement rather than resolving it. Kahn told residents in February 2026 that he would meet neighbours again sometime in March. On April 15, 2026 the company filed a site plan application for an industrial project, which was declared administratively complete on June 9, 2026 and is still pending before the Planning Board.

The options

Four concepts, and what the zoning already allows

Keep the dates attached to these numbers. The industrial concept presented to the Planning Board in September 2025 and the smaller one the developer showed at community meetings, reported in February 2026, are different proposals — and the larger figures belong to the earlier one.

Concepts presented for 199 Grandview Road, against the baseline of what the current zoning allows.

What the zoning allows

Keenan's reading, June 2025

What it is
Houses on large lots under the current zoning
Scale
About 1.6 million sq ft plus 13 homes
Affordable homes
None
Traffic as presented
Not stated in these terms
Buildout
Not stated
Where it stands

By-right industrial

Presented September 8, 2025

What it is
Houses on large lots under the current zoning
Scale
About 1.6 million sq ft plus 13 homes
Affordable homes
None
Traffic as presented
Not stated in these terms
Buildout
Not stated
Where it stands

Industrial

Community meetings, reported February 2026

What it is
Houses on large lots under the current zoning
Scale
About 1.6 million sq ft plus 13 homes
Affordable homes
None
Traffic as presented
Not stated in these terms
Buildout
Not stated
Where it stands

All-residential

Community meetings, reported February 2026

What it is
Houses on large lots under the current zoning
Scale
About 1.6 million sq ft plus 13 homes
Affordable homes
None
Traffic as presented
Not stated in these terms
Buildout
Not stated
Where it stands

Mixed-use

Community meetings, reported February 2026

What it is
Houses on large lots under the current zoning
Scale
About 1.6 million sq ft plus 13 homes
Affordable homes
None
Traffic as presented
Not stated in these terms
Buildout
Not stated
Where it stands

Sources: the September 8, 2025 Planning Board presentation for the 2025 industrial figures — where the by-right build-out was given as 402 truck trips and more than 8,000 total trips in a 24-hour period, the car share of that total having been read into the record from the developer's traffic summary at the June 23, 2025 hearing as 7,820 car trips; the three concepts Kahn showed at informal community meetings, as reported by The Monty News in February 2026, for the rest; former Mayor Devra Keenan, reading the assessor's records aloud at the June 23, 2025 hearing, for the 16-to-80-home baseline. Blank cells mean the figure was not given, not that it is zero.

The developer's account of how it arrived here comes from the press, not the meeting record. Eli Kahn told The Monty News in February 2026 that township officials had suggested to him fifteen months earlier that they wanted affordable housing on the site, and that he was still trying to learn what the township would accept:

We're frustrated because we're trying to get input and trying to get some ideas from them as to what they would accept, what residents would like to see here… Something's going to happen to this property. Let's try to make something that works for the majority of the people.
Eli Kahn, February 2026, as reported by The Monty News

The meeting record cuts the other way. Five months before that interview, at the September 8, 2025 Planning Board meeting, E. Kahn's own planner told the board “the township did not lead us in any direction” on the alternative concepts.

The point that makes the industrial concept matter politically is that it needs nobody's permission on density. Light manufacturing is what the Limited Manufacturing zone is for. A site plan that conforms to the zoning is reviewed for its engineering, not for whether the township wants it. That is the fact underneath both the township's willingness to study a redevelopment designation and the residents' unwillingness to see one.

June 2026

The data-center ban

Montgomery prohibited data centers townwide, and prohibited detention centers in the same ordinance.

On June 8, 2026 the Planning Board recommended the ordinance and, in the same minutes, found it consistent with the Master Plan. The board also asked the governing body to exempt the Montgomery Township Police Department from the definition of a detention center, because as drafted the prohibition appeared to outlaw the township's own holding cells. The adopted text contains no such carve-out.

The Township Committee adopted Ordinance No. 26-1779 on June 18, 2026 by 4 to 0. That is not a five-member unanimous vote: Deputy Mayor Vince Barragan resigned effective that evening, the seat was vacant for the vote, and Patricia Taylor Todd was elected Deputy Mayor and sworn in the same night. The operative sentence is short: “Data centers are specifically prohibited throughout Montgomery Township.” The stated rationale was energy usage, increased electrical demand, noise from cooling equipment and large water consumption, and the ordinance recites the general purpose of ensuring orderly development and protecting existing residential, commercial and environmental resources.

The public hearing drew both sides. Craig Gianetti of Day Pitney LLP appeared for E. Kahn Development in opposition. Speaking in support were Dawn Cohen; Mary Reece, chair of the Montgomery Environmental Commission; Nancy Herrington; Mike Pisauro, policy director of The Watershed Institute, who said the Institute was part of a coalition seeking a statewide data-center moratorium and cited New Jersey drought conditions, cost increases across the PJM region and a noise lawsuit over a Vineland data center; Jenny Psaki of Cranford; and Kendra DiPaola.

Source Township Committee — June 18, 2026 watch the township video The resignation, the public hearing and the adoption vote are all in this meeting.

July 2026

The lawsuit

E. Kahn asked the Superior Court to void the ordinance. It did not ask Montgomery for $300 million.

On July 31, 2026 E. Kahn Development Corp. filed suit in Somerset County Superior Court seeking a declaration that Ordinance 26-1779 is invalid and unenforceable, together with an injunction against its enforcement. The complaint argues that the Planning Board's June 8 recommendation lacked a documented discussion of whether the ordinance was consistent with the township Master Plan.

That allegation can be checked against the record, and it is worth checking. The approved June 8, 2026 minutes state that the board found the ordinance to be consistent with the Master Plan. Whether that finding is sufficient is a question for the court, and this page does not guess at the answer.

September 17, 2026

The redevelopment study

Two resolutions, adopted 4 to 0 with one member absent. Both are narrower than the headline suggests, and the study was not the township's idea.

Resolution #26-9-260 directs the Planning Board to conduct a preliminary investigation into whether the property at 199 Grandview Road designated as Lot 2 in Block 14001 meets the criteria for designation as a non-condemnation redevelopment area. Resolution #26-9-261 authorises an escrow funding agreement with E. Kahn Development Corp. to pay the costs of that study.

Three limits belong with any account of this vote. The study covers only Block 14001 Lot 2 — not Block 13001 Lot 15, the other parcel. The designation contemplated is non-condemnation, which carries no eminent-domain power. And the vote was 4 to 0 with Committeeman Mike Martin absent; Mayor Singh said on the record that he was sick. Herring, Ahn, Deputy Mayor Taylor Todd and Mayor Singh voted yes. The township attorney stressed that the study authorises no plan and approves no project; a planner's report goes to the Planning Board in public before anything else can happen.

Asked directly by resident Paul Hao whether the resolutions had been requested by the developer or were the committee's own idea, the answer from the dais was unambiguous.

That's his request. Yes. It's his request.
From the dais, Township Committee, September 17, 2026

Two members explained their votes. Committee Member Ahn framed a yes as preserving options — he said the study could let the township look at hospitals and other possibilities — against a by-right limited manufacturing facility that would bring a lot of trucks and lights at night. Deputy Mayor Taylor Todd said: “I want us to have options and the ability to have a say in what happens. So I'm voting yes.”

Bruce Afran's statement for Save Montgomery was read into the public record that night. It argued that a designation “will fail in the courts if it amounts to cherry picking isolated incidents of repair or maintenance needs, and fails to identify true blight on the property,” and that “the Kenvue buildings are largely in a pristine state and are well suited to their intended uses, or can be adaptively reused.” Save Montgomery said it intends to use all the resources at its disposal to fight the study and to oppose any plans for a high-density housing development on the site.

Source Township Committee — September 17, 2026 watch the township video from 1:53:20 As of September 20, 2026 no news outlet had reported the outcome of this vote; this account rests on the township's own video and agenda.

The other side

The township's case

There is a real argument for keeping options open, and it is mostly about money.

Mayor Singh set it out on September 17, 2026, after the township's affordable-housing counsel told the Committee that Kenvue would cease operations at the site by the end of the year. The township expects a revenue gap of roughly $1.4 million a year as a result, and the owner has already signalled that he will seek a tax appeal once the buildings empty — which, if successful, would widen the gap rather than close it. Singh also said the township had approached the New Jersey EDA and Somerset County about buying the property, without success.

Set against that is the by-right alternative. If nothing changes, the owner can build light manufacturing without asking the township's permission on density, and the traffic figures in the table above are the developer's own. A redevelopment designation would give the township a seat it does not otherwise have. That is the case the four members who voted yes actually made.

The counter-argument is equally concrete. A designation requires the property to meet statutory criteria, and Save Montgomery's position is that buildings in good condition do not meet them. Both propositions will be tested by the planner's report, in public, before the Planning Board.

Ahead

What happens next

Four things are open at once, and none of them is finished.

  • The study. The Planning Board conducts the preliminary investigation and reports in public. Only after that can the Township Committee consider a designation, and only for Block 14001 Lot 2, and only on a non-condemnation basis.
  • The industrial site plan. Filed April 15, 2026, administratively complete since June 9, 2026, and still unscheduled.
  • The data-center suit. Filed July 31, 2026; the township said on September 17 that it had not been served.
  • The housing case. Settled with Fair Share Housing Center, but not certified by the court. See Round Four, Explained.

All of these are decided in public meetings. The Township Committee generally meets on the first and third Thursday of the month; the Planning Board generally on the second and fourth Monday; the Zoning Board of Adjustment generally on the fourth Tuesday. All three move and skip meetings, so check the township's board meeting calendar before you go.

This story on the timeline

Each entry carries its own citations and, where a meeting exists, a deep link into the township video.

  1. Milestone Kenvue winds down Skillman as it moves to SummitKenvue, the consumer-health company spun out of Johnson & Johnson, disclosed in a 2023 SEC filing that it would move its headquarters from Skillman to Summit; through 2024 it wound the Skillman campus down — 51 layoffs filed under the WARN Act in February 2024 — putting the future of the former J&J campus at 199 Grandview Road in play for the first time in decades.
  2. Milestone Planning Board opens the Fourth Round hearing — 417 units on the Kenvue siteThe Planning Board opened its public hearing on the Fourth Round Housing Element and Fair Share Plan, whose two inclusionary sites Headline News Montgomery totalled at 597 units, and which put 417 of them, 70 affordable, on the former Kenvue campus. The meeting ran about three hours — roughly the first half-hour a presentation, the rest questions, never reaching public comment — and the hearing was carried to June 26.
  3. Milestone E. Kahn lays out its concepts for 199 Grandview RoadWith no formal application before the board, no township professionals to review it and no board opinion on the merits, the campus's contract purchaser laid out for the Planning Board the concepts it had been showing township staff since August 2024 — a by-right industrial build-out, a mixed-use plan, an all-residential concept, and the 417-unit plan the township had adopted.
  4. Milestone E. Kahn files a general development plan for light industrial useThe developer filed a general development plan for an industrial build-out of the campus. The Planning Board declined to hear it, on advice that Montgomery has no ordinance authorizing general development plan review — a refusal the developer then took to court.
  5. Milestone The sale of the campus closesThe sale closed in or around December 2025 or early January 2026 — the only dating on the public record — about sixteen months after the buyer first showed concepts to township staff.
  6. Milestone The township says the Kenvue site is coming out of the housing planIn an affordable housing update moved to the top of the agenda, the township attorney said Montgomery had notified the court program it would amend its plan, and that with the Pike Run extensions no other development would remain in it — naming the Kenvue site and Thrive. 23 Orchard Road came out too, though she did not name it that night. The Committee then adopted the $1.1 million bond ordinance.
  7. Pending E. Kahn files a site plan for an industrial project at the campusWith the site out of the housing plan, the owner filed an ordinary site plan application under the property's existing zoning. E. Kahn's own complaint dates the filing to April 15, 2026 and says the application was declared administratively complete on June 9; the township's records confirm the application exists and conforms to the LM zone, but do not carry those dates.
  8. Resolved Data centers and detention centers banned townwideThe Township Committee adopted Ordinance #26-1779, prohibiting data centers and detention centers throughout Montgomery Township, on a 4-0 roll call after a public hearing at which E. Kahn's lawyer asked it to reject or carry the ordinance and six speakers — four of them Montgomery residents — spoke in support.
  9. In court E. Kahn sues to void the data-center ordinanceE. Kahn Development Corp. filed suit in Somerset County Superior Court seeking a declaration that Ordinance 26-1779 is invalid and unenforceable and an injunction against its enforcement. Widely repeated reports that the suit demanded $300 million were wrong, and the township said so on the record.
  10. Active Committee orders a redevelopment study of the Kenvue siteThe Township Committee adopted Resolutions #26-9-260 and #26-9-261 by 4-0, with Committeeman Mike Martin absent, directing the Planning Board to investigate whether Block 14001, Lot 2 at 199 Grandview Road meets the criteria for designation as a non-condemnation redevelopment area, and funding that study through an escrow agreement with E. Kahn Development Corp.

The documents behind this page

Primary records, linked where the township and the courts publish them.

Sources

Where each claim on this page comes from. Where reporting and the primary record disagree, the primary record is used and the disagreement is noted.

  1. 2025 Fourth Round Housing Element and Fair Share Plan (Montgomery Township / Clarke Caton Hintz) The source of the 382.771-acre figure and of the 417-unit allocation to the site.
  2. Planning Board meeting video, June 23, 2025 About three hours on the Fourth Round plan, most of it questions; the assessor-record acreage breakdown is read aloud near 1:50:20.
  3. Planning Board meeting video, September 8, 2025 The conceptual presentation of the Kenvue site plans, including the 2025 by-right industrial figures.
  4. Township Committee meeting video, September 17, 2026 The redevelopment-study vote, the tax-gap figures, the correction of the reported damages claim, and the statement that the study was the owner's request.
  5. Township Committee minutes, June 18, 2026 Adoption of Ordinance 26-1779, and the resignation that left the fifth seat vacant that night.
  6. Planning Board minutes, June 8, 2026 The Board's recommendation, its Master Plan consistency finding, and its request for a police carve-out.
  7. Ordinance No. 26-1779, as noticed by the township
  8. Township Committee agenda, September 17, 2026
  9. Headline News Montgomery: 417 homes proposed for Kenvue site, residents push back hard
  10. The Monty News: Kenvue site on Montgomery Committee agenda tonight
  11. The Monty News: a New Jersey town draws a line against the AI boom and detention facilities
  12. Patch: Montgomery faces lawsuit challenging data center ban Useful on the filing itself. Reports of a $300 million demand, which circulated widely, describe a different case in another municipality.
  13. New Jersey Monitor: NJ data center bans and the courts
  14. Montgomery Township: board meeting calendar The live calendar. All three boards move and skip meetings.