The record

Timeline

Every dated step in the fight over Montgomery Township’s Fourth Round housing plan and the former Kenvue campus at 199 Grandview Road — assembled from township minutes, resolutions, agendas and meeting video, with the citation for each one attached to the entry.

Entries
32
Citations
74
Meetings on the record
13
Covering
2024 — 2026

Where this stands

The 382.771-acre former Kenvue campus at 199 Grandview Road (Block 14001 Lot 2 and Block 13001 Lot 15), whose Limited Manufacturing core is about 257 acres, entered public life here as the largest site in Montgomery’s Fourth Round Housing Element and Fair Share Plan: 417 units, 70 of them affordable, on a campus zoned Limited Manufacturing. After a year of hearings, mediation and an amended plan, the site is no longer in the plan. That is a real change. The township’s own explanation was an agreement in principle with the owner of Pike Run to extend controls on at least 96 existing units — verbal and unexecuted when it was announced on December 4, 2025 — which filled the plan without new construction. Staff had told the Planning Board on June 23, 2025 that the same owner “were not able to agree to extend the controls”; the public record does not explain why that position changed, and this site does not speculate about it. Residents had objected on the record through a year of hearings, and two citizen groups were objectors in the case.

It is not the end of the story. Three fronts are open.

  • The housing plan is not certified. The township has a settlement with Fair Share Housing Center, but on September 17, 2026 its attorney said on the record that the settlement is not final until a court approves it at a compliance hearing, that the judge will not hold one until the township has met with E. Kahn Development, and that without it Montgomery could lose its immunity from builder’s-remedy lawsuits.
  • The data-center ban is in court. Ordinance 26-1779, which prohibits data centers and detention centers townwide, was adopted 4-0 on June 18, 2026 — a four-member vote because the fifth seat was vacant that night. E. Kahn Development sued on July 31, 2026 to have it declared invalid and its enforcement enjoined.
  • A redevelopment study is under way. On September 17, 2026 the Committee adopted Resolutions 26-9-260 and 26-9-261 by 4-0, with Committeeman Mike Martin absent, directing the Planning Board to investigate whether Block 14001, Lot 2 meets the criteria for a non-condemnation redevelopment area. The study covers only that lot, carries no eminent-domain power, and — asked directly from the floor — the dais said it came at the developer’s request.

The township’s side of this is on the record too, and belongs here. Kenvue is expected to cease operations at the site by the end of 2026; Mayor Neena Singh said the township anticipates a roughly $1.4 million annual tax-revenue gap as a result, with the owner already signalling a tax appeal. Committee members framed the study as preserving a say in what happens next rather than accepting a by-right industrial build. Readers can weigh that against the entries below; the sources are there for exactly that purpose.

Where the press got something wrong, this timeline says so and cites the correction. The most repeated example: reports that E. Kahn sought $300 million in damages from Montgomery. That reporting was wrong. The township attorney corrected it on the record on September 17, 2026 — there is no such demand in the suit against Montgomery, and the figure belongs to a case brought against a different municipality.

How to read an entry

  • 8 entries are marked “Key moment.” They carry a heavier rule and a larger headline — the pivots in the story.
  • Status says where a thing stands: milestone, resolved, active, in court, or pending.
  • Sources close every entry. Where an event happened at a catalogued meeting, a “Watch this moment” link opens the township’s video at the exact second.

Jump to: 2026 2025 2024

Filter the timeline

Topic
Status

Showing all 32 entries

2026 17 entries

  1. The Kenvue site Pending

    Kenvue is due to cease operations at the site — link to this entry

    The township attorney told the Township Committee on September 17, 2026 that Kenvue will cease operations at 199 Grandview Road by the end of the year; Mayor Neena Singh said the township expects a resulting gap of roughly $1.4 million a year in tax revenue, with the owner having already signalled a tax appeal.

    Kenvue’s departure has been in progress since 2024, but the operational end date matters on its own, and it is the reason the township leaned on hardest when it defended acting rather than waiting.

    The township attorney said operations at the site end by the close of 2026. Mayor Singh put the numbers on the record the same night: a roughly $1.4 million annual gap in tax revenue, and E. Kahn Development signalling a tax appeal. That was not a surprise from nowhere. The developer’s own presenter told the Planning Board in September 2025 that the property was assessed at $41.6 million, was Montgomery’s second-largest tax generator, was over-assessed by more than 60 percent in his view, and that “a tax appeal will be coming,” which he estimated at a short-term reduction of $700,000 to $800,000 a year.

    This is the fiscal case the township made from the dais — the resolution itself recites only the statutory criteria, and the dais confirmed the same night that the study was the developer’s request — and it deserves to be stated as the township states it. A large ratable going quiet is a real municipal problem whatever one thinks of the remedy. It is also worth keeping in proportion: the appeal turns on what the property is worth, and the argument the presenter made for that was a use argument — a 1970s single-tenant office campus, he said, now trades at land value minus demolition. A redevelopment designation does not by itself replace a dollar of revenue either.

  2. The Kenvue site Active Key moment

    Committee orders a redevelopment study of the Kenvue site — link to this entry

    The Township Committee adopted Resolutions #26-9-260 and #26-9-261 by 4-0, with Committeeman Mike Martin absent, directing the Planning Board to investigate whether Block 14001, Lot 2 at 199 Grandview Road meets the criteria for designation as a non-condemnation redevelopment area, and funding that study through an escrow agreement with E. Kahn Development Corp.

    Two limits belong in every account of this vote. The study covers only Lot 2 in Block 14001 — not the rest of the campus, and so not the whole 382.771-acre holding. And the designation contemplated is non-condemnation, which carries no eminent-domain power. Committeeman Douglas Herring, Ahn, Deputy Mayor Taylor Todd and Mayor Singh voted yes; Martin was absent, and the mayor said on the record that he was sick. The fifth seat was filled that night, so this 4-0 is an absence — unlike the 4-0 votes of June 18, 2026, which reflect a vacancy.

    The township attorney stressed what the vote was not: the study “does not authorize a plan… does not green light any project.” A planners’ report goes to the Planning Board in public, the board recommends back, the Committee holds a hearing, and only then could a designation be made. Nor is the mechanism new here: in October 2025 the Committee directed the same board to investigate 23 Orchard Road for a non-condemnation designation.

    Whose idea it was, is not in doubt. Resident Paul Hao asked from the floor whether the two resolutions were the developer’s request or the Committee’s own idea. The answer from the dais: “That’s his request. Yes. It’s his request.”

    The Committee’s case was largely fiscal. The township attorney said Kenvue will cease operations at the site by the end of 2026; Mayor Singh said the township expects a roughly $1.4 million annual gap in tax revenue, and that E. Kahn has already told township staff it will come to the township seeking relief on the emptied buildings’ assessment. Committee Member Ahn said a no vote would leave the by-right limited manufacturing complex the developer has presented — trucks and lights all night — and that only the study opens other options.

    Roughly forty minutes of public comment ran heavily against it. A statement from Bruce Afran, attorney for Save Montgomery — a grassroots group of Montgomery Township residents — was read into the record, arguing a designation resting on cherry-picked maintenance needs rather than true blight will fail in court.

  3. Affordable housing Pending Key moment

    The housing case is not over: no compliance hearing, no certification — link to this entry

    On the same night, the township attorney said Montgomery has reached a settlement with Fair Share Housing Center but that it is not final until a court approves it at a compliance hearing — one the judge would not hold until the township sat down with E. Kahn Development, a meeting that has now taken place. Without a hearing, the attorney said, the township could lose its immunity from builder's-remedy lawsuits.

    This is the least reported and most important fact on the page. The removal of the Kenvue site from Montgomery’s Fair Share Plan is real and it is adopted. But the plan has not been certified. No compliance hearing has been held, no Judgment of Compliance and Repose or Compliance Certification has issued, and no final judgment has been entered.

    The attorney’s account was specific: the settlement with Fair Share Housing Center “is not final until it is reviewed by the court and approved by the court in what’s called a compliance hearing,” and “the judge has advised us that he will not entertain a compliance hearing until we have sat down with [E. Kahn] Development.” That meeting has since happened — following the judge’s directive, the attorney said, the township has now met with E. Kahn Development about the Kenvue site. Asked what follows if there is no hearing, the attorney said Montgomery would not be in compliance and the township could lose its immunity from builder’s-remedy lawsuits.

    That is the thread connecting the two votes taken later the same evening to the housing case. Anyone who tells you this fight is finished is ahead of the record.

  4. Litigation In court Key moment

    E. Kahn sues to void the data-center ordinance — link to this entry

    E. Kahn Development Corp. filed suit in Somerset County Superior Court seeking a declaration that Ordinance 26-1779 is invalid and unenforceable and an injunction against its enforcement. Widely repeated reports that the suit demanded $300 million were wrong, and the township said so on the record.

    The relief sought, as reported, is a declaration that the ordinance is invalid and unenforceable, plus an injunction barring its enforcement. One of the complaint’s arguments, as described in the reporting on it, is that the Planning Board’s June 8 recommendation lacked documented discussion of the ordinance’s consistency with the township master plan — and if that is what the complaint says, the board’s own minutes do not bear it out, since they state the consistency finding in terms.

    We publish no damages figure, because none is verified. Several outlets reported that the suit sought more than $300 million from Montgomery — NJ.com on August 13, 2026, and a cluster of radio-station sites the next day. On September 17, 2026 the township attorney told the Committee the complaint had been read and that it contains no such demand, attributing the figure to reporting on a lawsuit filed in a different municipality. Press reporting identifies that case as Hexa Builders’ suit against Monroe Township in Gloucester County. As of September 17 the township had not been served, so the case had not begun.

  5. Affordable housing Pending

    Committee authorizes a settlement with Fair Share Housing Center — link to this entry

    Returning from executive session at 10:18 p.m., the Township Committee adopted Resolution #26-6-194 authorizing a written Fourth Round settlement agreement with Fair Share Housing Center on the terms of the amended plan the Planning Board adopted in March. A settlement is not a judgment.

    The quiet item of the night, added after the ordinance everyone had come for. The resolution passed 4-0 — a four-member Committee voting, the fifth seat vacant since Vince Barragan’s resignation was announced at the start of the same meeting.

    Its recitals are useful history, and they are the best primary chronology of the case on the public record: the declaratory judgment action filed January 29, 2025 (Docket No. SOM-L-153-25, from the caption read into the March 19, 2026 minutes); Judge Mennen’s March 27, 2025 order setting the obligations; the Land Use Board’s adoption of the original plan on June 26, 2025; challenges filed in 2025 by E. Kahn, by Montgomery Neighbors United and by Savemontgomery.org; the Program decision of March 4, 2026 and the court’s acceptance of it on March 5; the amended plan filed with the court March 11, 2026; and Fair Share Housing Center — the statewide affordable-housing advocate that is a party to the case — finding the amended plan compliant subject to conditions.

    A settlement is a real step, but it is not a judgment. And this settlement is with Fair Share Housing Center, which had asked only for more documentation — not with E. Kahn, the party that fought the plan. The judge has said he will not entertain a compliance hearing until the township sits down with E. Kahn. As of September 2026 no compliance hearing had been held and no Judgment of Compliance and Repose or Compliance Certification had issued, which is why the township’s immunity from builder’s-remedy lawsuits remained contingent.

  6. Data centers Resolved Key moment

    Data centers and detention centers banned townwide — link to this entry

    The Township Committee adopted Ordinance #26-1779, prohibiting data centers and detention centers throughout Montgomery Township, on a 4-0 roll call after a public hearing at which E. Kahn's lawyer asked it to reject or carry the ordinance and six speakers — four of them Montgomery residents — spoke in support.

    The ordinance amends Chapter 16 of the Land Development Code to add two lines to the prohibited uses — “Data centers are specifically prohibited throughout Montgomery Township” and the same for detention centers — plus definitions of both, with the detention-center definition reaching private and government facilities alike. The recitals cite electrical demand, noise from cooling equipment, water consumption and incompatibility with surrounding land uses, and, for detention facilities, public safety and emergency-services demands.

    Ayes: Martin, Ahn, Deputy Mayor Taylor Todd and Mayor Singh. This is a 4-0 vote because the fifth seat was vacant — Vince Barragan’s resignation was announced at the start of that same meeting — not because a member was absent.

    One thing the Planning Board asked for did not survive. On June 8 the board had recommended that the governing body add language exempting the Montgomery Township Police Department from the detention-center definition, because the draft appeared to reach the township’s own holding cells. The ordinance as adopted contains no such carve-out; the definition runs to facilities “established and maintained by a private or government entities.” What a court would make of that, if anything, is not something this site will predict.

    Craig Gianetti of Day Pitney, for E. Kahn Development, argued a blanket prohibition must bear a reasonable relationship to a legitimate planning objective, and that the land use law contemplates asking where a use can go rather than eliminating it. Six speakers backed the ban — four Montgomery residents, plus the Watershed Institute’s policy director and a Cranford resident — on energy, water, noise, and, for the detention half, the 1,500-bed facility proposed in Roxbury.

  7. Process and deadlines Resolved

    Vince Barragan resigns; Patricia Taylor Todd is elected Deputy Mayor — link to this entry

    Mayor Neena Singh opened the June 18, 2026 meeting by announcing that Deputy Mayor Vince Barragan had resigned from the Township Committee effective that day. Patricia Taylor Todd was nominated, elected Deputy Mayor for 2026 and sworn in the same night, leaving the Committee at four members.

    Barragan had been re-elected only seven months earlier, in November 2025, and had sat as Deputy Mayor through the whole period in which the Kenvue site came out of the housing plan — though he was absent from the March 19, 2026 meeting that endorsed the amended plan. The minutes record the resignation as effective June 18, 2026 and give no reason. From the dais that night, the newly sworn Deputy Mayor Taylor Todd said Barragan had moved out of town and had said so in his resignation letter. Dennis Ahn nominated Patricia Taylor Todd as Deputy Mayor, Mike Martin seconded, and she was elected and sworn in that evening.

    This small piece of housekeeping is worth knowing because of what it does to the vote counts on this site. Every roll call taken on June 18, 2026 — including the adoption of Ordinance #26-1779 and the Fair Share Housing Center settlement resolution — is a 4-0 vote because the fifth seat was vacant, not because anyone was absent. By September 17, 2026 the seat had been filled by Douglas Herring, and the 4-0 votes taken that night are 4-0 for the opposite reason: Committeeman Mike Martin was absent.

    Two identical tallies, two different explanations. Anywhere this site writes 4-0, it says which one applies.

  8. The Kenvue site Pending

    The industrial site plan is declared administratively complete — link to this entry

    Patch reported that on June 9, 2026 the township declared E. Kahn's site plan application administratively complete, starting the statutory clock for a Planning Board hearing. The company's lawyer confirmed on the record nine days later that the application was deemed complete. More than three months later it still had no hearing date.

    Completeness is an administrative finding, not an approval: it means the application contains the documents the ordinance requires, so the board can hear it. The June 9 date itself is Patch’s reporting; what is on the record is E. Kahn’s lawyer telling the Township Committee nine days later that “the application is deemed complete.” It matters here for two reasons.

    First, it was the basis of the argument that lawyer made to the Committee that night — that the by-right application had already been deemed complete, so the data-center ban could not reach it. He asked the Committee to table the ordinance, objecting both to what the ban forecloses in the future and to the ban itself as lacking a reasonable relationship to a legitimate zoning objective.

    Second, nothing has happened since. The township attorney told the Committee on September 17, 2026 that the by-right application is at the Planning Board but has not been scheduled, because of the issues being worked through in the affordable housing case. The Planning Board’s own future-agenda list on June 8, 2026 did not include it either.

  9. Data centers Resolved

    Planning Board finds the data-center ordinance consistent with the Master Plan — link to this entry

    On the statutory referral before adoption, the Planning Board voted 9-0 to recommend that the Township Committee adopt Ordinance #26-1779 and found the ordinance consistent with the Master Plan. That finding is the one E. Kahn's later complaint, as reported, says went undocumented — the complaint alleges the June 8 recommendation lacked any documented discussion of Master Plan consistency.

    Before a governing body adopts a zoning amendment, the Municipal Land Use Law requires it to refer the amendment to the Planning Board, which must report back within 35 days identifying any provisions inconsistent with the master plan. The board did that in about twelve minutes. Board Attorney Karen Cayci framed the motion in two parts — find the ordinance consistent with the Master Plan, and separately recommend that the governing body add language exempting the Montgomery Township Police Department, whose own holding cells appeared to fall within the draft definition of a detention center. The vote was 9-0.

    The minutes state the finding in terms: “The Board found the ordinance to be consistent with the Master Plan.”

    What is fair to the developer’s side is that the finding was stated rather than argued — the discussion was about definitions and a police carve-out, not about which master plan goals a ban serves. Whether a court treats a stated finding as sufficient is an open question. The recommended police exemption did not make it into the adopted ordinance.

  10. The Kenvue site Pending

    E. Kahn files a site plan for an industrial project at the campus — link to this entry

    With the site out of the housing plan, the owner filed an ordinary site plan application under the property's existing zoning. E. Kahn's own complaint dates the filing to April 15, 2026 and says the application was declared administratively complete on June 9; the township's records confirm the application exists and conforms to the LM zone, but do not carry those dates.

    This is the route the township said was open to the owner all along. After the Planning Board declined to hear a general development plan — Montgomery has no ordinance authorizing GDP review — counsel told the February 2026 Planning Board that the applicant retained the right to file a site plan or seek an informal concept review. The zoning is limited manufacturing — a distinction resident Dave Leonard corrected from the floor that September, telling the Township Committee “multiple times people say light manufacturing, that’s not what the zoning is.”

    It also fixes the rules the application is judged by. Under New Jersey’s time-of-application rule, an application for development is generally reviewed against the ordinances in force when it was submitted, though later ordinances relating to health and public safety can still apply. E. Kahn’s lawyer told the Township Committee in June that because the application had already been deemed complete, the data-center ban would not reach it.

    As of September 17, 2026 the Planning Board had not scheduled it. The township attorney said that was because of the issues being worked through in the affordable housing case.

  11. Affordable housing Resolved

    Township Committee endorses the amended plan — link to this entry

    The Township Committee endorsed the 2026 Amended Fourth Round Housing Plan Element and Fair Share Plan by Resolution #26-3-113, adopted 3-0 as part of the consent agenda with Ahn and Deputy Mayor Barragan absent, completing the municipal side of the amendment.

    The plan document on the township’s website carries both dates on its cover: adopted March 9, 2026 and endorsed March 19, 2026. The reason the two dates are ten days apart is on the March 5 record — the February hearing lost to the blizzard.

    With endorsement, everything Montgomery could do by itself was done: a plan adopted, an implementing ordinance rewritten, a spending plan, an administrative agent, an affirmative marketing plan, and $1.1 million appropriated to pay for the extensions the plan relies on. What remained was not in the township’s hands. The plan still needed a court, and six months later it had not had one.

  12. Process and deadlines Pending

    Deadline to adopt the amended plan and implementing ordinances — link to this entry

    March 15, 2026 was the deadline for municipalities to complete adoption of their Round Four implementing documents, with the plan itself to be filed with the state within 48 hours of adoption and no later than March 16. The blizzard-delayed Planning Board hearing left Montgomery filing against it.

    The second hard date in the Round Four schedule. Having missed the February 23 hearing to a blizzard, Montgomery adopted the amended plan on March 9 and told the Planning Board the document would go to the state within 48 hours and no later than March 16.

    The governing body’s endorsement could not be squeezed in before the deadline, so the township expected to ask the court for the extra days and endorsed the plan on March 19. The township attorney said on March 5 that Montgomery was far from the only municipality asking for that accommodation. Nothing in the record we have reviewed suggests the delay cost the township anything.

  13. Affordable housing Resolved Key moment

    Planning Board adopts the Amended Fourth Round plan, 8-0 — link to this entry

    After a hearing of about twenty minutes at which no member of the public spoke, the Planning Board adopted the 2026 Amended Fourth Round Housing Element and Fair Share Plan on an 8-0 roll call — 275 credits from 210 preserved units plus 65 bonus credits, against an obligation of 260. The Kenvue site carries no credits in it.

    Board planner Michael Sullivan set out the arithmetic: McKinley Court, 60 senior rentals extended, 58 creditable under the state cap plus 17 bonus, for 75; McKinley Commons, 35 ownership units; Montgomery Glen, 19; Pike Run, controls extended on 96 of its 210 family rentals with 48 bonus credits, for 144; plus two third-round surplus credits. Total: 210 preserved units and 65 bonus credits — 275 against 260, a surplus of 15.

    Ayes: Battle, Blodgett, Khan, Mani, Roberts, Schuldiner, Singh and Glockler. Nobody spoke at the hearing.

    Staff were candid about what was still open. The township was by then in Superior Court rather than the dispute resolution program, had received an order days earlier extending its immunity through the amendment, and still needed the court’s approval of the plan itself.

    There is also a soft spot in the 275. Counsel disclosed that the McKinley Court and McKinley Commons extensions are conditional — their inclusion is premised on mutually acceptable discussions with that owner. Those controls do not expire until 2032, so there is time, and the 2030 state midpoint review is the fallback checkpoint if terms are never reached. Between them the two McKinley developments account for 110 of the 275 credits, which is why the 15-credit surplus is not as comfortable a margin as it looks.

    Pike Run, which carries another 144, rests on a change of position the public record does not explain: in June 2025 the township said it had reached out to the owner and “they were not able to agree to extend the controls.” The record shows the owner came forward after the June 2025 adoption and that the township reported an agreement in principle with that owner on November 13, 2025 — but nothing explaining why the position changed, and we do not speculate about it.

    The Kenvue site carries no credits in the amended plan. It survives only in the plan’s procedural history, which records E. Kahn’s objection to its removal and Save Montgomery’s support for it.

  14. Litigation Pending

    Program judge reports no consensus; a fairness hearing comes next — link to this entry

    The township attorney reported that the program judge had told the Mount Laurel judge no consensus was reached with the objectors, and that the next step is a fairness hearing before any order issues. The Committee adopted the rewritten Chapter 15 ordinance and the amended spending plan, each 5-0.

    Township Attorney Wendy Rubinstein Quiroga’s account: Program Judge Miller had sent his recommendation to Judge Mennen, no consensus was reached with the objectors, the recommendation was to give deference to the municipality on the plan it chooses, and the next step is a fairness hearing on the new plan before an order issues. She added that the adjudicator had indicated the plan appears compliant, while noting it had only been filed in February.

    The Monty News reported this stage as the dispute resolution program recommending approval and finding the plan constitutionally compliant. That framing is the newspaper’s; the township’s own minutes describe what is set out above, and no program recommendation document is posted on montgomerynj.gov.

    The Committee also adopted Ordinance #26-1771 and Resolutions #26-3-100, #26-3-101 and #26-3-102 — the spending plan, the administrative agent and the affirmative marketing plan — all 5-0. The machinery moved; the case did not close.

  15. Process and deadlines Pending

    The February 23 Planning Board hearing is noticed, then cancelled — link to this entry

    The public hearing at which the Planning Board was to adopt the amended housing plan was advertised for February 23, 2026 and then cancelled because of a blizzard. It was re-noticed and held on March 9.

    The township itself announced, at the February 9, 2026 information session, that the Planning Board would hold the public hearing and adopt the amended plan on February 23. It did not happen that day. The meeting is listed as cancelled on the township’s Agenda Center, the March 19 Township Committee minutes record that the hearing was postponed by a blizzard, and there is no meeting video for that date because there was no meeting.

    The township re-advertised with the full ten days’ notice required, which pushed the hearing two weeks. The consequence was procedural but real: because the Planning Board had not adopted the plan, the Committee could not endorse it before the March 15 filing deadline, and expected to ask the court for the extra days. The township attorney told the Committee on March 5 that Montgomery was far from the only municipality in that position.

  16. Affordable housing Pending

    Township Committee is briefed and introduces the implementing ordinance — link to this entry

    The township planner repeated the amended-plan presentation for the full Township Committee, which then introduced Ordinance #26-1771, repealing and replacing Chapter 15, "Affordable Housing," on first reading. Residents used public comment to press for no zoning change at 199 Grandview Road.

    The presentation covered the same ground as February 9: Round Four runs 2025 to 2035 with a state midpoint review in 2030; the obligation is 260 credits; the amendment meets it by extending controls on existing units rather than by zoning new inclusionary development. The planner noted the township’s Third Round plan, adopted in 2008, had been amended in 2010, 2018 and 2020 — precedent for amending a fair share plan mid-round.

    Introduction of Ordinance #26-1771 passed on four ayes: Ahn, Taylor Todd, Deputy Mayor Barragan and Mayor Singh. Committeeman Martin was absent; Committeeman Ahn arrived at 7:06 p.m., before the vote. Township Attorney Wendy Rubinstein Quiroga described the ordinance as adopting the state’s model language so the statutory citations are current, not as a substantive change.

    Answering Nancy Castilino, who asked the Committee to leave the existing light industrial zoning alone, the dais said nothing in the housing plan contemplates a zoning change at the site, and that any change would require an ordinance, a noticed hearing and written notice to every owner within 200 feet.

  17. Affordable housing Pending

    Planning Board information session on the amended plan — link to this entry

    A 30-minute information session, not a hearing: staff walked the Planning Board and the public through the draft amendment that drops the E. Kahn/Kenvue site, 23 Orchard Road and Thrive Assisted Living in favour of extending affordability controls on existing units. No vote was taken.

    Township Administrator and Planning Director Lori Savron explained the basics first: a housing plan element sits inside the master plan, and a master plan is policy — it does not itself rezone anything. Staff then went through the credit arithmetic, development by development, against a 260-credit obligation, with bonus credits capped by the state at 25 percent of the allocation.

    The amendment followed eight months of public objection, and Planning Board Chairman Dave Campeas said from the dais that the public had been heard. The township’s own stated reason, given from the podium on February 9 and again on February 19, was narrower: since the June 2025 plan was adopted, circumstances had changed to let the township extend controls on existing units instead.

    Campeas, quoted by The Monty News on the amendment: “The public spoke and we listened. We came up with a different plan that hopefully … makes a lot more sense for the township.”

    Staff also laid out a schedule — draft posted February 13, ordinance introduced February 19, Planning Board hearing February 23, Committee endorsement March 5 — and were clear about the limit of all of it: removing the site from the housing plan does not decide what gets built there.

2025 14 entries

  1. The Kenvue site Pending Key moment

    The township says the Kenvue site is coming out of the housing plan — link to this entry

    In an affordable housing update moved to the top of the agenda, the township attorney said Montgomery had notified the court program it would amend its plan, and that with the Pike Run extensions no other development would remain in it — naming the Kenvue site and Thrive. 23 Orchard Road came out too, though she did not name it that night. The Committee then adopted the $1.1 million bond ordinance.

    This is the meeting where the change residents had asked for since June was stated on the record, and where the township said exactly what would replace 417 homes: extended deed restrictions on existing affordable units, paid for with a $1.1 million appropriation — $650,000 from the township’s COAH trust fund and $450,000 in bonds or notes. Ordinance #25-1766 was adopted that night after a public hearing.

    One member framed the trade honestly: other parties had offered to fully fund the extensions in return for staying in the plan, it was clear the community did not want that, and so the township paid for them itself instead.

    It settled less than it sounded like. A letter putting the program and the parties on notice is not an amended plan, and an agreement in principle is not an executed one. Nor is the turn it rests on explained: staff had told the Planning Board on June 23, 2025 that the same Pike Run owner “were not able to agree to extend the controls,” and the public record does not explain why that position changed. We do not speculate about it. The attorney said the plan itself would not be amended until the new year, after a publicly noticed Planning Board hearing, and that no party had been declared right or wrong about anything yet.

  2. The Kenvue site Pending

    The sale of the campus closes — link to this entry

    The sale closed in or around December 2025 or early January 2026 — the only dating on the public record — about sixteen months after the buyer first showed concepts to township staff.

    Through the whole 2025 argument the buyer was under contract rather than on the deed — “equitable owners,” as Eli Kahn described it to the Planning Board in September. Former Mayor Devra Keenan had made the same point in June: the township was negotiating a housing plan around a property still titled to Johnson & Johnson.

    Exactly who holds it now is itself disputed. At two public meetings, in February and again in September 2026, Skillman resident Lloyd Fernandez told officials that the deeds of record name four single-member limited liability companies rather than E. Kahn Development Corp., and that the June 2025 commitment letter came from 199 Grandview Partners LLC. The township attorney said in September 2026 that the site “is solely owned now by” E. Kahn Development. We have not examined the deeds ourselves, and we report the disagreement rather than resolve it.

  3. Affordable housing Pending

    First mediation session; the township signals it will amend its plan — link to this entry

    At the first settlement conference in the Round Four case, and in a letter that followed, Montgomery notified the state's dispute resolution program and every interested party that it would amend its housing plan — because an agreement in principle with the owner of Pike Run, together with extensions already approved elsewhere, made the inclusionary sites unnecessary.

    The session was held by Zoom shortly after the November 13 meeting, with the parties in separate breakout rooms and the substance confidential. What the township attorney reported publicly on December 4 is that Montgomery had written to the program and to all interested parties saying it would amend its plan.

    The reason was a verbal, unexecuted agreement in principle with the owner of Pike Run to extend affordability controls on at least 96 rental units. Ninety-six, she said, “does get us to the full plan” — which is why no other development needed to stay in it. The full plan also counted the 54 ownership-unit extensions the Committee had approved on November 13 and additional senior rentals at McKinley Court.

    The same owner had been approached in 2025 and, staff told the Planning Board on June 23, “were not able to agree to extend the controls.” By November 13 that had already changed: the attorney told the Committee there was an agreement in principle with the owner of Pike Run, and the mayor described the earlier difficulty in the past tense. Why the owner’s position changed is not stated anywhere in the public record, and this site will not guess at it.

    She also set out the posture of the case, and it is worth keeping straight. Fair Share Housing Center had not objected to Montgomery’s plan. Two citizen groups objected to the inclusion of the Kenvue site. The site’s purchaser objected to those objections. No party had yet been declared right or wrong about anything.

  4. Affordable housing Resolved

    A $1.1 million bond and the first extensions of affordability controls — link to this entry

    The Township Committee introduced a $1,100,000 bond ordinance to pay for extending affordability controls on existing affordable homes, adopted the first two extension resolutions covering 54 owner-occupied units, and adopted a resolution ratifying a settlement agreement. Every recorded vote was 5-0.

    This is where the alternative to building on the Kenvue site stopped being an idea and became a budget line. Ordinance #25-1766 appropriated $1,100,000 — $650,000 from the township’s COAH (affordable housing) trust fund plus authorization to issue $450,000 in bonds or notes — to fund payments to owners of deed-restricted homes whose affordability controls were expiring.

    Resolutions #25-11-374 and #25-11-375 extended controls at Montgomery Hills (McKinley Court) and Montgomery Glen: 35 and 19 owner-occupied units. The mechanics matter for anyone who owns one. Controls are extended under the township’s existing right in the original deed restriction whether or not an owner opts in; opting in is what earns the additional $10,000 the bond pays for.

    Resolution #25-11-376, “Ratifying Settlement Agreement,” was adopted with a short explanation that it memorialized in open session terms discussed in closed session. Which case it settled was never stated when the vote was taken.

  5. Elections Resolved

    Incumbents hold both Township Committee seats — link to this entry

    Democrats Vincent Barragan and Michel "Mike" Martin, both incumbents, defeated Republicans Chris Venis and George DeSanctis for the two Township Committee seats.

    The election came four months into the argument over the Kenvue site, and it did not change the Committee. The Monty News reported that registered Democrats outnumber Republicans in Montgomery roughly two to one, and that it had been nearly nine years since township voters elected a Republican.

    The membership did change later, and not at the ballot box. Vincent Barragan resigned from the Committee effective June 18, 2026; Patricia Taylor Todd was elected Deputy Mayor that night. By September 2026 the Committee was Mayor Neena Singh, Deputy Mayor Taylor Todd, Dennis Ahn, Mike Martin and Douglas Herring.

    The steps that took the Kenvue site out of the housing plan fall in the weeks after this election: a bond ordinance introduced nine days later and adopted in December, the first mediation session on November 14, and an amended plan the Planning Board adopted in March 2026. The same five members did all of it. That is the order the events came in; nothing on the public record says the election produced them, and this site does not claim it did.

  6. Process and deadlines Resolved

    The Committee sends 23 Orchard Road for a non-condemnation redevelopment study — link to this entry

    Eleven months before it did the same thing at the Kenvue site, the Township Committee directed the Planning Board to investigate whether 23 Orchard Road meets the statutory criteria for designation as a non-condemnation redevelopment area, with the completed study expected back to the board around March 2026.

    This entry exists because of what it says about September 2026. The Township Committee’s order for a redevelopment study of the Kenvue site looks like a first for Montgomery. It is not.

    Township Administrator and Planning Director Lori Savron told the Planning Board on February 9, 2026 — and repeated it to the Township Committee ten days later — that in October 2025 the Committee had already authorized and directed the same Planning Board to conduct a preliminary investigation into whether 23 Orchard Road meets the criteria for designation as a non-condemnation redevelopment area, with the board expected to review the completed study around March 2026. Same statute, same kind of resolution, same absence of eminent-domain power.

    23 Orchard Road is the site the June 2025 housing plan had carried at 180 units, 36 of them affordable, and which the 2026 amendment also removed. A redevelopment designation is a tool Montgomery uses; whether the criteria are met on any particular property is a separate question, and it is the question the Kenvue study now has to answer.

  7. The Kenvue site Pending

    E. Kahn files a general development plan for light industrial use — link to this entry

    The developer filed a general development plan for an industrial build-out of the campus. The Planning Board declined to hear it, on advice that Montgomery has no ordinance authorizing general development plan review — a refusal the developer then took to court.

    A general development plan is a New Jersey mechanism for approving a large project in phases. Counsel later explained why developers like them: a GDP requires less documentation than a site plan and, in towns that have adopted the enabling ordinance, can shield a project from later zoning changes for years.

    Montgomery has no such ordinance, and therefore no standards to review a GDP against. Adopting one is not mandatory. On counsel’s advice the Planning Board declined to hear the application, telling the owner it remained free to file an ordinary site plan or to bring an informal concept plan for feedback.

    E. Kahn sued the Planning Board over the refusal. At the February 9, 2026 meeting counsel said the township had not yet been served; the case was still live in June 2026, when the board went into closed session on it. One resident called the dispute unnecessary confrontation; the board’s position was that it was a technical legal limit, not a choice.

  8. The Kenvue site Pending

    E. Kahn lays out its concepts for 199 Grandview Road — link to this entry

    With no formal application before the board, no township professionals to review it and no board opinion on the merits, the campus's contract purchaser laid out for the Planning Board the concepts it had been showing township staff since August 2024 — a by-right industrial build-out, a mixed-use plan, an all-residential concept, and the 417-unit plan the township had adopted.

    Chairman Dave Campeas opened by setting limits: no formal submission, no township professionals to review anything presented, no board opinion on the merits. Eli Kahn introduced himself and partner Matt Adams as “equitable owners” — under contract, not yet closed — and said they had bought the campus for its industrial zoning, not to build housing.

    Adams compared four scenarios: roughly 1.6 million square feet of flex light-manufacturing space plus 13 residential lots built by right over 10 to 15 years; a mixed-use plan; a 617-unit all-residential concept; and the township’s 417-unit plan. The by-right figures given that night were 402 truck trips and more than 8,000 total trips per 24 hours at full build-out — the developer put the car share at roughly 7,600, and the same traffic memo had been read into the record in June 2025 as 7,820 car trips — and impervious cover rising from about 36 acres to about 102. The trip counts, truck counts and impervious-cover figures were all the developer’s own, from consultants it hired — Kahn said so himself, “we didn’t come up with these numbers, we used consultants” — and residents called the report cherry-picked and designed to scare them.

    That is the September 2025 concept, and it should never be quoted as if it were the current one. At an informal neighbours’ meeting that November, reported in February 2026, the developer was presenting a smaller by-right scheme — roughly 1.2 million square feet plus 9 single-family homes, with 300 to 400 truck trips a day. Two different concepts, two months apart, on the same parcel.

    Two things from that night mattered later. The developer flagged a coming tax appeal, saying the property is over-assessed. And asked what happens if the township meets its obligation another way, the answer was that it would fight to stay in the plan — and failing that, build some version of the industrial project.

  9. Process and deadlines Pending

    Residents take the Kenvue plan to the Township Committee — link to this entry

    Nothing about the Kenvue site was on the Township Committee's agenda, but roughly 80 minutes of a two-hour meeting went to public comment about it. Officials corrected the unit numbers, explained why Montgomery had not challenged its state obligation, and promised town halls in August.

    The fight in June had been at the Planning Board, which adopts the housing plan. This was the first time the governing body heard it at length.

    Edward Silverman argued the adopted plan rested on two findings he considered false: that no architecturally important building would be affected, and that the site is underutilized. Shellie Jacobson, a Grandview Road resident since 1978, pointed to the two-lane bridges on Grandview and asked members to drive the road themselves. Dave Leonard asked for a written alternative plan within thirty days.

    From the dais, officials corrected the figure residents kept repeating: the township’s entire Round Four obligation is 260 units, not 250 low-income units on one site, and 70 affordable units were proposed at Grandview Road. Counsel explained that towns that put forward a lower number mostly moved it by six to ten units, and that the window to challenge comes only once every ten years; one committee member added that filing a challenge would have cost Montgomery its immunity. A member called the plan a living document — “always part of a master plan,” and subject to change.

  10. Process and deadlines Pending

    Statutory deadline to adopt a Housing Element and Fair Share Plan — link to this entry

    June 30, 2025 was the deadline under New Jersey's 2024 affordable housing law for municipalities to adopt a Fourth Round Housing Element and Fair Share Plan. Missing it would have cost Montgomery its immunity from builder's-remedy lawsuits.

    This date explains most of what happened in June 2025, and it deserves to be stated fairly. The 2024 legislation replaced the old COAH process with a schedule of deadlines, each of which a municipality must hit to keep its protection from builder’s-remedy litigation — the suits in which a developer asks a court to approve a project a town’s own zoning does not allow. Towns that lose that protection can effectively lose control of their planning.

    Montgomery’s professionals told the Planning Board that putting a ten-year plan together in ninety days was, in their words, extremely unheard of, and the resolution adopting the plan records the Board’s objection to the “unfair timeline” the state had imposed on municipalities. Round Four itself runs from 2025 to 2035, with a state midpoint review in 2030.

  11. Affordable housing Resolved Key moment

    Planning Board adopts the 2025 Fourth Round plan, eight to one — link to this entry

    After roughly two more hours of public comment, the Planning Board adopted the Fourth Round Housing Element and Fair Share Plan dated June 13, 2025 — the plan carrying 417 homes on the Kenvue campus — on a roll call of eight ayes and one no, four days before the state deadline.

    The continuation was called for 5:00 p.m. and ran to about 7:41. More than twenty residents spoke, nearly all opposed, on notice, on the plan’s finding that no architecturally important building was affected, and on alternatives the township had not costed.

    Two board members framed their votes as a legal judgment rather than a planning one: the 2024 state framework gave municipalities about ninety days to write a ten-year plan, and missing the June 30 deadline would end Montgomery’s immunity from builder’s-remedy litigation. Board member Paul Blodgett voted no, saying he could not reconcile a 260-unit obligation with a plan he believed had holes in it.

    The memorializing resolution recorded the board’s own objection to the state’s timeline and stated that the plan could be amended or supplemented if the need arose. Within nine months it was. One exchange that night explained why: the township had approached the owner of Pike Run about extending controls on its 210 affordable rentals, and the owner was not willing to participate — investors who put money into the property thirty years earlier, staff said, expected their return to come when the units shifted to market rate, and the township had no legal means to compel participation. Five months later that position had changed, and Pike Run became the centrepiece of the amended plan. The public record does not explain why the owner’s position changed, and we do not speculate about it.

  12. Affordable housing Pending Key moment

    Planning Board opens the Fourth Round hearing — 417 units on the Kenvue site — link to this entry

    The Planning Board opened its public hearing on the Fourth Round Housing Element and Fair Share Plan, whose two inclusionary sites Headline News Montgomery totalled at 597 units, and which put 417 of them, 70 affordable, on the former Kenvue campus. The meeting ran about three hours — roughly the first half-hour a presentation, the rest questions, never reaching public comment — and the hearing was carried to June 26.

    Township affordable-housing consultant Michael Sullivan presented a Fourth Round prospective obligation of 260 credits and a rehabilitation obligation of 73, met through extensions of expiring affordability controls and three inclusionary sites: 417 units on the Kenvue campus with 70 affordable, 180 units at 23 Orchard Road with 36 affordable, and assisted-living credits at Thrive.

    The board never reached the public comment period. About two and a half hours went to questions: how a site zoned for limited manufacturing, which permits no housing at all, could hold 417 homes when former Mayor Devra Keenan’s own arithmetic — worked live from the assessor’s records, on the roughly 160 acres she read as commercially assessed — produced 16 under mountain-residential zoning, 32 under R-5 and at most 80 under R-2; what the contingency plan was if the Kenvue deal collapsed; whether the headquarters building, which residents attribute to I.M. Pei & Partners, would be demolished, which the concept plan indicated it would.

    The township’s answer was consistently that the alternative was worse. Sullivan said replacing the site would require finding room for roughly 706 units elsewhere — because dropping Kenvue loses the on-site inclusionary units, the redevelopment bonuses and the developer-funded off-site extensions all at once. Asked directly what the contingency was, staff said past plans had carried backup alternatives but “we didn’t have any backup alternatives for this plan”; the board would simply have to come back and amend it. That is what happened: the township told the court in December 2025 that it would pull the site, and the Planning Board adopted the amended plan on March 9, 2026.

    No vote was taken. The hearing was carried to Thursday, June 26 at 5 p.m., four days before the statutory deadline. Some accounts date this first night June 24; the meeting video, the township’s minutes and the adopting resolution’s own recital all say June 23.

  13. Process and deadlines Pending

    Legal notice published for the Round 4 housing plan hearing — link to this entry

    Notice of the Planning Board hearing on Montgomery's Fourth Round Housing Element and Fair Share Plan was published in the legal advertisements of the Courier News, the township's official newspaper. The roughly 800-page plan itself went online the next day, ten days before the hearing.

    Headline News Montgomery dates the legal notice to June 12, 2025. The township’s own account at the June 23 hearing was that the plan went up on the township website on June 13, the day after the legal notice ran in the Courier News — ten days before residents would be asked to comment on it.

    That gap became the first grievance of the whole dispute. Residents said the legal ads in a county paper few of them read reached almost no one, and pressed on whether anyone living near the proposed sites had been mailed notice — the answer was that mailed notice comes later, when a builder files. The township’s answer was accurate as far as it went: for a master plan hearing state law requires publication in a designated newspaper plus service on neighbouring clerks and the county, which the clerk said had been done, and the 200-foot mailed notice residents expected attaches to zoning changes and site plan applications, not to adoption of a housing element.

  14. Litigation Resolved

    The court sets Montgomery's Fourth Round obligations — link to this entry

    Judge William G. Mennen entered the order fixing Montgomery's Fourth Round numbers — a present need of 73 units and a prospective need of 260 — in the declaratory judgment action the township filed on January 29, 2025, Docket No. SOM-L-153-25.

    Under the 2024 law that replaced the Council on Affordable Housing, a municipality that wants protection from builder’s-remedy litigation files a declaratory judgment action and joins the Affordable Housing Dispute Resolution Program. Montgomery did both on January 29, 2025, two days after the Township Committee accepted its numbers by Resolution 25-1-54. The case is Docket No. SOM-L-153-25, and it is the case everything since has run through — the one named, meeting after meeting, in the Township Committee’s executive-session resolutions on affordable housing from February 2026 onward.

    The order setting the obligations followed. Every plan, hearing and settlement described further down this timeline is measured against the two figures it fixed: 73 units of present need, meaning rehabilitation of existing substandard housing, and 260 units of prospective need for 2025 through 2035.

    Two township records date the order slightly differently. The recitals of Resolution #26-6-194, adopted June 18, 2026, give March 27, 2025; the recitals of Resolution #26-3-113, adopted March 19, 2026, give March 26. We use March 27, the date given in the later of the two recitals, and note the discrepancy rather than hide it.

2024 1 entries

  1. The Kenvue site Pending

    Kenvue winds down Skillman as it moves to Summit — link to this entry

    Kenvue, the consumer-health company spun out of Johnson & Johnson, disclosed in a 2023 SEC filing that it would move its headquarters from Skillman to Summit; through 2024 it wound the Skillman campus down — 51 layoffs filed under the WARN Act in February 2024 — putting the future of the former J&J campus at 199 Grandview Road in play for the first time in decades.

    The campus at 199 Grandview Road had been a Johnson & Johnson research and headquarters property. Residents told the Township Committee on July 17, 2025 that its late-modern office building was designed by Henry N. Cobb and W. Steven Wood of I.M. Pei & Partners with oversight by Pei himself — an attribution the township’s own 2025 housing plan did not acknowledge, having stated that there are “no historic or architecturally important sites or buildings on the property.” That plan puts the site at 382.771 acres, comprising Block 14001 Lot 2 and Block 13001 Lot 15; the Limited Manufacturing core that holds the buildings is about 257 acres. Reading the assessor’s records aloud at the June 23, 2025 Planning Board hearing, former Mayor Devra Keenan put about 160 of those acres in the commercial (class 4B) assessment, at a net value of roughly $41 million, with a further 97 acres nearby carried as farm-qualified. For years the site was one of the township’s largest taxpayers.

    The relocation itself was disclosed in a 2023 SEC filing. What 2024 held was the wind-down: 51 layoffs filed under the WARN Act in February, and a long-term lease on a Summit campus beginning in 2025. When Kenvue said it was leaving, a large, well-serviced industrial property — with its last employees due out by 2026 — became the obvious candidate for several different questions: where Montgomery could put state-mandated affordable housing, what a developer could build by right, and what the township could afford to lose from its tax base. Those three questions have been argued over ever since.